Most of the arguments we see between a roofer and a customer start the same way. Somebody asked for a quote, somebody went up a ladder and had a proper look, and then the two things got mashed into one email with a price at the bottom.

They are different documents. They do different jobs, they carry different risk, and one of them is work you can charge for.

What a quote actually is

A quote is an offer to do defined work for a defined price. It is a commercial document. Once the customer accepts it, you are contractually on the hook for what it says, so the useful parts are the boundaries.

A quote should say what you are doing, what you are not doing, what you have assumed, how long the price holds, and what happens if you open up the roof and find something else. If a quote runs to four lines and a figure, every assumption in your head is now an assumption in the customer's head too, and theirs will be more generous than yours.

What a quote does not do is explain the roof. It does not record condition, it does not grade defects by urgency, and it does not tell the customer what happens if they do nothing. That is the report's job.

What a survey report actually is

A survey report is a record of condition on a date. It is evidence. It says what you saw, where you saw it, what it is doing to the building, and how urgent it is.

A decent roof report has the address and the date, the weather and access conditions on the day, what you could and could not inspect, the construction as found, the defects with photographs and locations, a grading of each defect, and recommendations. Indicative costs can sit in there as a guide, but they are not a quote, and the report should say so in those words.

The difference matters most in the limitations section. A quote has no honest way of saying "I could not lift tiles at the valley because the scaffold stopped short". A report does, and that single sentence is often what keeps you out of trouble eighteen months later.

If you want to see the shape of one before you write your own, there is a sample roof survey report you can read end to end, and a longer walkthrough on how to write a roof survey report covering the wording for each section.

Side by side

Quote Survey report
Purpose Offer to carry out work Record of condition on a date
Core content Scope, price, exclusions, validity Defects, photos, grading, limitations
Who it protects Both parties, commercially Mainly you, evidentially
Typical charge Free Charged, or credited against the job
Life after the job Spent once accepted Useful for years

When to charge for the report

The honest test is how much of your time is in it. A twenty minute look from a ladder with a photo of a slipped tile is pre-sales. A two hour inspection with a drone or a scaffold tower, lifted tiles, loft access, moisture readings and six pages of write-up is professional work, and you should be paid for it.

Three ways roofers handle it, all defensible:

  • Free visual appraisal, then a priced report if the customer wants the detail.
  • Fixed report fee, credited in full against the works if you get the job.
  • Fixed report fee, not credited, because you are selling independent advice and the customer may use it to go elsewhere. Managing agents and landlords often prefer this.

Say which one you are doing before you go. "The survey is £X, and I'll take that off the job if you go ahead" is a five second sentence that stops the whole misunderstanding.

One thing to get straight in your own head: if you charge for the report, you owe a duty of care for what is in it. That is an argument for better limitations wording, not for refusing the fee. If you are not a chartered surveyor, do not write like one, and do not stray into structural opinion you cannot support. Say what you saw, say what you could not see, and recommend a structural engineer where it belongs.

How the report protects you when they take the cheaper quote

This is the part roofers underrate. You survey a roof, you find failed mortar bedding on the ridge, perished felt at the eaves and three cracked slates over the bathroom. You price a proper job. Another firm quotes half, points the ridge and leaves.

Eighteen months later the customer is back, wet ceiling, and the conversation is suddenly about who said what.

If all you ever issued was a quote, you have a number and a scope line. If you issued a report, you have dated photographs, a graded defect list, a note that the eaves felt was perished along the full rear elevation, and a recommendation the customer read. You are no longer arguing about memory.

It also protects you at the point of sale. A customer comparing your price against a cheaper one is usually comparing two scopes they do not understand. A report gives them something to hold the cheap quote against. "Does your price include the eaves felt the surveyor flagged?" is a question that either gets answered or quietly ends the competition.

And it protects you from scope creep. When the customer later says "I thought that was included", the report shows what was identified, and the quote shows what was priced. Two documents, two jobs, no overlap.

Make the report signed, not just sent

A report that sits unread in an inbox is weak evidence. A report the customer has opened, read and signed is strong.

Get an acknowledgement. It does not have to be a legal ceremony. A simple acceptance page where the customer signs to confirm they have received and read the report, with the date and time recorded, closes the loop. If they decline the recommended works, note that in the file too, in neutral wording: "Client advised that the recommended eaves repair would be deferred." No commentary, no blame, just the record.

Issue the report first, then the quote, and reference the report in the quote by date and reference number. That ordering makes the logic obvious to anyone reading the file later, including a loss adjuster.

Keep the two documents separate

Tempting as it is to send one PDF with the condition notes at the top and a price at the bottom, resist it. Mixing them means your limitations and caveats end up attached to a contractual offer, and the customer reads the whole thing as a sales document rather than advice.

Separate files, separate references, cross-referenced to each other. The report dated and signed, the quote with its own validity period and exclusions.

This is the workflow Docutrades was built around, as it happens: notes and photos on site, one press to tidy the wording, a branded PDF the customer signs on their phone before you have left the drive. The 14-day trial includes five reports if you want to run a real job through it.

The sentence to say on the doorstep

"I'll do a survey and give you a written report on the condition of the roof, with photos and priorities. That's £X. Then I'll quote separately for whichever bits you want doing, and the report fee comes off the job."

Pick the version that matches how you work, write it on a card, and use the same words every time.

Next time you go out, write the report and the quote as two files, and get a signature on the report before you discuss the price. Keep both in the job folder with the photos, because the day you need them is the day you cannot go back and take them.

Written and edited by the Docutrades team. Published 9 October 2026.